For information about major construction projects, please visit projects.ttc.ca.

Learn about when and why TTC needs to complete overnight construction to keep transit moving.

Learn about the causes of subway noise and vibration and TTC’s work to address it.

Bay Station - Easier Access Project

Elevators entered service on December 30, 2020

Bloor and Yonge area - survey work, utility and geotechnical investigations

December 12 to April 6, 2021

Bloor-Yonge Station - platform design investigations

November 30, 2020 to March 31, 2021

Bus stop improvements

Bus stop improvements for accessibility and to accommodate articulated buses - July 2020 update

Chester Station - Second Exit/Entrance and Easier Access project update

Elevators available for service use as of September 2, 2020. Second Exit/Entrance scheduled for completion by the end of 2021.

College Station - Second Exit/Entrance and Easier Access project

Overnight work week of January 18

Danforth Avenue at Oak Park Avenue - underground utility chamber rebuild

As early as November 9 for approximately 8-10 weeks

Donlands Station - second exit/entrance and Easier Access project update

Preliminary investigative work ongoing

Dupont Station is accessible - Easier Access Project Update

Fall 2020

Dupont Street at Kendal Avenue - underground utility chamber rebuild

Starting January 11 for 8 to 10 weeks

Greenwood Station Easier Access (elevator) project - preliminary investigative activities

Ongoing

Kennedy Station - Eglinton Crosstown construction

May 1, 2017 until approximately 2021

Kipling Station - Metrolinx construction impacts

Reduced parking and access changes at Kipling Station

Lansdowne Station - Easier Access Project 

Elevator construction in Green P Car Park 81 begins June 2019 until end of 2021

Runnymede Station - Easier Access Project

Runnymede Station is TTC's 50th accessible station

Russell Carhouse - acoustic wall (along Minto Street)

Construction to start as early as January 4, 2021

Sherbourne Station - Easier Access Project

August 2019 to end of 2021

Station Improvements and Maintenance - Tile and Panel Replacement

Work to remove and replace tiles, ceiling and wall panels is ongoing at some stations

Summerhill Station - Easier Access project

Utility investigations - December 7 to 24

Waterfront East LRT neighbourhood - survey work, utility and geotechnical investigations

November 16, 2020 to March 31, 2021

Wheel-Trans Access Hubs

Ongoing construction at various locations

Wilson Station - elevator construction

Elevators entered service on December 18, 2020

Wilson Station - temporary closure of Tippet Road commuter lot

Additional commuter parking available at Spadina Subway Extension stations and Yorkdale Station

90 Vaughan route improvements

Starting May 10, 2020